Greenland Mines Delivers Two Key Milestones at Skaergaard: Bathymetric Survey Completed, Initial Metallurgical Core Drilling Concluded

August 17, 2026 9:00 AM EDT

Survey vessel M/V Byr returns safely to Iceland having covered more area with water depth data (bathymetry) than originally planned

High-resolution seabed data already used to safely anchor support vessel Argus within 500 meters of the western outcropping mineralized zone at Skaergaard

Data advancing toward official navigational charting and future shipping infrastructure planning for the Project's next development phase

Initial HQ drill core supporting the metallurgical bulk sample successfully completed, with the program shifting to NQ-size core drilling from a newly established, fully operational core... More