Applied Digital brings 175 MW online at Polaris Forge 1 campus

Go back to Applied Digital brings 175 MW online at Polaris Forge 1 campus

Applied Digital Delivers Second Building at Polaris Forge 1

July 1, 2026 1:00 PM EDT

On-time delivery of Building 2 Phase 1 reinforces Applied Digitals repeatable model for turning power into operational AI capacity

DALLAS, July 01, 2026 (GLOBE NEWSWIRE) -- Applied Digital (NASDAQ: APLD), a designer, builder, and operator of high-performance, sustainably engineered data centers and colocation services for artificial intelligence, cloud, networking, and blockchain workloads, today announced it has achieved Ready for Service for Phase 1 of Building 2 at Polaris Forge 1, delivering 75 MW of operational AI capacity to its customer on schedule and bringing total live capacity at the campus to 175 MW.

The... More