Lithium Americas provides $1.6 billion capex guidance for Thacker Pass

Go back to Lithium Americas provides $1.6 billion capex guidance for Thacker Pass

Lithium Americas Provides a Project Update and 2026 Capex Guidance for Thacker Pass

February 19, 2026 6:55 AM EST

(All amounts in US$ unless otherwise indicated)

VANCOUVER, British Columbia--(BUSINESS WIRE)-- Lithium Americas Corp. (TSX: LAC) (NYSE: LAC) (Lithium Americas or the Company) provides a project update for the year ended December 31, 2025, 2026 capital expenditure (Capex) guidance and 2026 project development milestones for its Thacker Pass project in Humboldt County, Nevada (Thacker Pass or the Project).

2025 was a pivotal year for Lithium Americas and the Thacker Pass Project with Phase 1 construction well underway, said Jonathan Evans, President and Chief Executive Officer of Lithium Americas. Safety... More