Uganda revamps century-old rail network after China delays funding
A commuter train is seen at the Uganda Railways Corporation (URC) headquarters in Kampala, Uganda November 5, 2019. REUTERS/Stringer
By Elias Biryabarema
KAMPALA (Reuters) - Uganda will begin refurbishing its century-old rail network this month to boost bulk cargo transportation, after failing to secure $2.2 billion in Chinese funding for a new standard-gauge line, a senior rail official said on Wednesday.
The rehabilitation will be carried out in phases over several years and cost at least 241 million euros ($267 million), Charles Kateeba, managing director of the state-run Uganda Railways Corporation, told Reuters.
The European Union has given a grant of 21.5 million euros and the railway corporation is talking to international development lenders for the rest.
Former colonial power Britain built the meter-gauge, 1,266 km (790 mile) network a century ago, mainly to move copper and other commodities.
But the network fell into disrepair during years of political upheaval and economic instability.
Now old, dilapidated engines hiss and clatter as they trundle between crumbling platforms, pulling drab carriages behind them. In many places, grass has grown over disused or missing tracks.
"Due to lack of maintenance over the years, most of the network is now in disuse," Kateeba said. "We shall replace some areas which have been either removed by vandals or are badly worn."
French firm Sogea-Satom will undertake the works, which include installing rocks ballast on sections, re-laying of tracks, flattening sections and repairing about 500 freight wagons.
CHINA HOPES DASHED
Bulk cargo transporters have been eager for cheaper transport and were disappointed when China did not offer funding for the Ugandan section of the Standard Gauge Railway (SGR) regional project.
It was originally designed to connect Kenya's Indian Ocean seaport of Mombasa to a vast hinterland including Uganda, South Sudan, Rwanda and Burundi.
Kenya has developed a section of the SGR from Mombasa to Nairobi with funding from China, but had to fund an expansion itself.
Ugandan authorities have been negotiating with China for more than five years, hoping for funds to construct its own SGR branch. But Kateeba said several factors, including Uganda's delayed oil production, delayed a credit deal.
Uganda discovered 6 billion barrels worth of crude oil more than 12 years ago in the west, but disagreements between the government and oil firms over tax and development strategy have repeatedly delayed production.
China's CNOOC <0883.HK> co-owns the fields with other firms. The Ugandan government now says it expects production to start by 2022 at the earliest.
If oil production had begun, Kateeba said, economic growth would mean "we would be able to really afford the credit.
"China is not giving us charity," he said.
Now China is examining whether repayments could be adjusted, costs lowered or the implementation period pushed back, he said.
(Reporting by Elias Biryabarema; editing by Katharine Houreld and Mike Collett-White)
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Why stocks held up despite rising yields and $100 oil? These 2 words explain it
- US jury says Apple owes record $5.7 billion in haptic technology patent case
- Northern Ireland court allows Protestant march in Catholic area, Sky News reports
Create E-mail Alert Related Categories
ReutersRelated Entities
Crude OilSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share