NTEC Statement on Appeal of the No Name Permit

The No Name Permit does not involve a new mine. It is not a new lease. It is a standard federal requirement whereby federal or Indian mineral lessees – such as NTEC – obtain approval to include additional area as part of their reoccurring 5-year Mine Plan Permit, the permit issued by Office of Surface Mining, Reclamation, and Enforcement (OSMRE) that authorizes NTEC to conduct mining operations. For nearly five decades, the
There are multiple permits within a lease that every surface coal mining entity must obtain prior to actively mining coal. Depending on where the mine is physically located, some of these permits are granted at a federal level, some may be granted at a state level, and some may even be granted at a local level. Recently, OSMRE approved two different "permits" for
This is not a new mine.
OSMRE's Record of Decision expressly finds that the No Name Permit does not propose expanding operations onto any lands not previously approved for mining. The 11,526-acre No Name permit area lies entirely within the existing Navajo
This is not a 110-year approval.
Actual authorization for on the ground mining activities at
The review was not "fast-tracked."
The approval followed a multi-year federal review under NEPA, SMCRA, the Endangered Species Act, the National Historic Preservation Act, and the Clean Water Act, with the Navajo Nation as a cooperating agency. OSMRE's own record documents extensive public notice, including newspaper notices and multiple public locations where the application was available for review. Multiple federal agencies reviewed the permit, and OSMRE ultimately concluded that approval was consistent with federal law and in the public interest.
The community was consulted, and it supports this permit.
The application for the No Name Permit has been transparent and conducted in full accordance with the law. As a Navajo-owned company, NTEC is committed to working in partnership with the Navajo Nation Government and Community to ensure that our operations benefit the economic, financial, social and cultural well-being of the Navajo Nation. Throughout the permitting process, we have worked closely with the Chapters and community to educate them on the project and continuation of the
- NTEC has made a total of 83 presentations to the Navajo community on the future operations of the
Navajo Mine , including:- 81 presentations to Chapters, Districts and Agencies
- 2 presentations at new Chapter Official orientation and training sessions
- NTEC obtained 21 resolutions supporting the continued operation of the
Navajo Mine , including resolutions from:- All 5 Agency Councils
- Districts 13 and 18
- 14 Chapters spread across all 5 Agencies including
San Juan , Nenahnezad, Upper Fruitland and Burnham Chapters
- In addition, NTEC has specifically reviewed its pending No Name Permit application at the Chapter, District and Agency levels on multiple occasions.
- Northern Agency passed a resolution overwhelming voting in favor of the No Name permit. This is in addition to resolutions from
District 13 , and Upper Fruitland,San Juan , Burnham, and Nenahnezad Chapters.
- Northern Agency passed a resolution overwhelming voting in favor of the No Name permit. This is in addition to resolutions from
Burnham Chapter, which opponents repeatedly cite as opposing the mine, is among the chapters that passed a resolution specifically supporting the No Name Permit.
How many families will be impacted by the permit and what will happen to them?
Despite repeated suggestions from opponents to the permit that large numbers, there are only three potentially affected permittees. The No Name Permit does not immediately remove these permittees from the land or eliminate grazing activities. Grazing continues until specific areas are formally needed as mining progresses. This is all performed in direct coordination with the very few remaining permittees.
The potential and orderly progression of mining activities at the
In addition, cultural protections are in effect and mandated by federal and tribal law. The No Name Permit must fully comply with Section 106 of the National Historic Preservation Act, and a Programmatic Agreement is being developed to ensure formal consultation with the Navajo Nation Tribal Historic Preservation Officer throughout the life of authorized mining.
The federal record DOES address water and reclamation.
OSMRE found the permit will not impact any significant waterways, streams, or Wild and Scenic study rivers. OSMRE also found that the mine's extensive existing water monitoring program directly addresses the concerns raised. After mining, the land will return to rangeland for grazing and wildlife habitat, the same as its pre-mining use. In 2025, NTEC returned a 2,211-acre reclaimed parcel to the Navajo Nation. It was the first time any mining company has fully reclaimed coal mine land to modern standards and returned it to Bureau of Indian Affairs jurisdiction.
This is a Navajo decision.
NTEC contributes more than
View original content to download multimedia:https://www.prnewswire.com/news-releases/ntec-statement-on-appeal-of-the-no-name-permit-302898841.html
SOURCE Navajo Transitional Energy Company
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- THE RITZ-CARLTON NAPLES, TIBURÓN REVEALS TRANSFORMED RESORT AND DYNAMIC CULINARY CONCEPTS
- Zen Tax Recognized Among the Top 4 Bookkeeping Companies in Toronto in New 2026 Study
- The Harvest Yard is Officially Open
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!





Tweet
Share