Finland's Oldest Nuclear Reactor Decommissioned in Espoo: VTT Info
The FiR1 research reactor was
Despite the reactor's small size, the FiR1 decommissioning project will domestically serve as a model for decommissioning commercial nuclear reactors and created new expertise for the benefit of VTT's and Fortum's international customers.
"The process of decommissioning a nuclear reactor has now been comprehensively tested in
The reactor was shut down in 2015, which initiated the licensing process for decommissioning and the planning for dismantling. In 2020, a significant milestone was reached when the spent fuel was transferred to
Alongside the FiR1 project, VTT, in collaboration with several Finnish partners, also executed the dECOmm development project funded by Business Finland. This project used the decommissioning project as a test platform for various applicable technologies and has successfully achieved its initial goal of exporting technology.
"During the project, our reputation has spread, and VTT will be involved in similar decommissioning projects abroad, both in research reactors and commercial power plants," Airila rejoices.
Having ambitious and measurable safety goals, the project brought together VTT's safety culture experts and the project leaders, facilitating an extraordinarily fruitful interaction. The experts closely supported the project lead in continuously enhancing the organization's safety culture, so they also gained hands-on experience from a real use case over several years. Now, VTT can use this experienced and cross-disciplinary team to offer unique safety culture support to other safety-critical projects.
Decommissioning Accelerated by Thorough Planning
In 2021, VTT received the decommissioning license for FiR1 from the Finnish government. Fortum, the main contractor, began dismantling in
"The dismantling phase was very swift, thanks to thorough planning and preparatory work. Additionally, it was crucial that we could leverage the strong nuclear safety culture and expertise from Fortum's Loviisa nuclear power plant. Fortum handled everything safely, efficiently, and on schedule without significant delays," says Airila.
Dismantling amid Aalto University's Otaniemi campus posed its safety requirements in organising the dismantling site and the arrangement of necessary waste transports.
The demolition waste which is classified as radioactive is being delivered for final disposal at Fortum's Loviisa nuclear power plant's low- and intermediate-level waste repository. A total of approximately 60 cubic meters of this waste, mainly concrete, was generated for delivery to the Loviisa repository. A six-meter-high water tank and a two-meter-thick concrete shell surrounded the reactor.
"For us at Fortum, this successful project is a testament to our extensive expertise, covering the entire lifecycle of a nuclear facility. We have executed a nuclear facility decommissioning project with the same quality and competence with which we have operated nuclear facilities and delivered projects for external customers over decades," says Antti Ketolainen, Fortum's director in charge of the project.
A significant experience for both VTT and Fortum was the preparation of a decommissioning and dismantling plan required for the decommissioning license. Extensive documentation was produced and developed for this purpose.
"We gained a lot of lessons and experience from the FiR1 project, which we can use to develop our operations and support our service business customers, for example, in preparing decommissioning plans and cost estimates," Ketolainen continues.
The decision to cease using the FiR1 reactor was made in 2012, and soon after, an environmental impact assessment for decommissioning commenced. The total decommissioning costs amounted to approximately
About 40 individuals worked on the decommissioning site at various stages and in shifts. Some VTT employees had worked with the reactor for decades. Three to four workers primarily carried out the actual dismantling, with others managing waste disposal, radiation monitoring, and site supervision.
More information:
Markus Airila, principal scientist, VTT, +358403508669, [email protected]
Antti Ketolainen, director, Fortum, Decommissioning and Waste, Nuclear Services, +358407518956, [email protected]
Further information on VTT:
Pepita Wakkola
Manager, Communications
+358 50 360 7242, [email protected]
www.vtt.fi
This information was brought to you by Cision http://news.cision.com
https://news.cision.com/vtt-info/r/finland-s-oldest-nuclear-reactor-decommissioned-in-espoo,c4002338
The following files are available for download:
https://news.cision.com/vtt-info/i/website-ydinreaktorin-purku-vtt,c3311801 | website-ydinreaktorin-purku-vtt |
https://news.cision.com/vtt-info/i/vtt-fir1-timeline,c3311807 | VTT FiR1 timeline |
View original content:https://www.prnewswire.com/news-releases/finlands-oldest-nuclear-reactor-decommissioned-in-espoo-vtt-info-302175019.html
SOURCE VTT Info
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Actions will help translate vision for Sino-US ties into reality: China Daily editorial
- Bitcoin Live News: BTC Gains 0.10% to $84,093 as Apeing’s $106K+ Presale Builds Momentum in the Next Big Crypto Market
- Quant (QNT), Plasma (XPL) or AlphaPepe? Best Crypto To Buy Now Buyers Chase the $0.03111 Coin Heading to $1
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share