Close

Final module placed for Vogtle 3 & 4 project

720,000-pound water tank placed atop Unit 4 containment vessel Represents last major crane lift for the construction project

April 26, 2021 7:15 AM EDT

ATLANTA, April 26, 2021 /PRNewswire/ -- All modules for Georgia Power's Vogtle 3 & 4 nuclear expansion project near Waynesboro, Georgia, have now been set as a massive water tank has been lifted into place atop the Unit 4 containment vessel and shield building roof. The placement also represents the last major crane lift at the project site.

The Passive Containment Cooling Water Storage Tank, known as CB-20, is a major part of the AP1000 reactor's advanced passive safety system. Standing 35 feet tall and weighing more than 720,000 pounds, the large component will hold approximately 750,000 gallons of water ready to flow down in the unlikely event of an emergency to help cool the reactor. The water can also be directed into the used fuel pool, while the tank itself can be refilled from water stored elsewhere on site.

The AP1000 plant's passive safety systems require no operator actions to mitigate potential emergency situations. These systems use only natural forces such as gravity, natural circulation and compressed gas to achieve their safety function. No pumps, fans, diesels, chillers or other active machinery are used, except for a few simple valves that automatically align and actuate the passive safety systems.

The modules used for Vogtle units 3 & 4 were made in advance of arriving to the project site and ready to be assembled into larger components that make up the nuclear units. Since 2011, major modules were delivered to the site by rail and truck and included a range of plant components such as floor and wall sections and supporting structures that surround the containment buildings and reactor vessels.

The final major module arrived at the construction site in late 2019, meaning all 1,485 major modules required to complete construction had been manufactured and safely delivered.

Significant milestones that have been recently achieved include:

  • Unit 4 Starting Integrated Flush - This test pushes water through the permanent plant system piping that feeds into the reactor vessel and reactor coolant loops. Integrated flush represents a critical step as the process is key to helping ensure the safe startup of Unit 4 and marks the start of extensive testing ahead for the unit's systems.
  • Unit 3 Nuclear Fuel Receipt - The first nuclear fuel assemblies for Unit 3 arrived at the site in December.
  • Unit 3 Condenser Vacuum Test - The test was conducted with the main turbine on turning gear and by operating supporting systems to establish the condenser vacuum, which is necessary to demonstrate the steam supply and water-cooling systems operate together and are ready to support hot functional testing and initial fuel load in the reactor.
  • Completion of Unit 3 Cold Hydro Testing - Confirmed the reactor's coolant system functions as designed and verified the welds, joints, pipes and other components of the coolant system and associated high-pressure systems do not leak when under pressure.

Carbon-free energy sourceThe new Vogtle units are an essential part of Georgia Power's commitment to deliver safe, clean, reliable and affordable energy for customers and play a significant role in supporting Southern Company's goal of net-zero carbon emissions by 2050.

Once operating, the two new units at Plant Vogtle will be able to power more than 500,000 homes and businesses. A diverse fuel mix, including nuclear, is also essential to maintaining a reliable and affordable energy infrastructure that attracts new investment, supports economic growth and creates jobs.

With more than 7,000 workers on site, and more than 800 permanent jobs available once the units begin operating, Vogtle 3 & 4 is currently the largest jobs-producing construction project in the state of Georgia.

Follow the progress being made at the site of the nation's first new nuclear units in more than 30 years through the Plant Vogtle 3 & 4 Online Photo Gallery and Georgia Power's YouTube channel.

About Georgia PowerGeorgia Power is the largest electric subsidiary of Southern Company (NYSE: SO), America's premier energy company. Value, Reliability, Customer Service and Stewardship are the cornerstones of the company's promise to 2.6 million customers in all but four of Georgia's 159 counties. Committed to delivering clean, safe, reliable and affordable energy at rates below the national average, Georgia Power maintains a diverse, innovative generation mix that includes nuclear, coal and natural gas, as well as renewables such as solar, hydroelectric and wind. Georgia Power focuses on delivering world-class service to its customers every day and the company is recognized by J.D. Power as an industry leader in customer satisfaction. For more information, visit www.GeorgiaPower.com and connect with the company on Facebook (Facebook.com/GeorgiaPower), Twitter (Twitter.com/GeorgiaPower) and Instagram (Instagram.com/ga_power).

Cautionary Note Regarding Forward-Looking StatementsCertain information contained in this release is forward-looking information based on current expectations and plans that involve risks and uncertainties. Forward-looking information includes, among other things, statements concerning the expected schedule for construction and start-up of Plant Vogtle Units 3 and 4, expected job creation and carbon emissions reduction goals. Georgia Power cautions that there are certain factors that can cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of Georgia Power; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Georgia Power's Annual Report on Form 10-K for the year ended December 31, 2020, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: the potential effects of the continued COVID-19 pandemic; the ability to control costs and avoid cost and schedule overruns during the development, construction, and operation of facilities or other projects, including Plant Vogtle Units 3 and 4, which includes components based on new technology that only within the last few years began initial operation in the global nuclear industry at this scale, due to current and future challenges which include, but are not limited to, changes in labor costs, availability and productivity, challenges with management of contractors or vendors, subcontractor performance, adverse weather conditions, shortages, delays, increased costs, or inconsistent quality of equipment, materials, and labor, contractor or supplier delay, delays due to judicial or regulatory action, nonperformance under construction, operating, or other agreements, operational readiness, including specialized operator training and required site safety programs, engineering or design problems, design and other licensing-based compliance matters, including, for nuclear units, inspections and the timely submittal by Southern Nuclear of the Inspections, Tests, Analyses, and Acceptance Criteria documentation for each unit and the related reviews and approvals by the U.S. Nuclear Regulatory Commission ("NRC") necessary to support NRC authorization to load fuel, challenges with start-up activities, including major equipment failure, or system integration, and/or operational performance, and challenges related to the COVID-19 pandemic; legal proceedings and regulatory approvals and actions related to construction projects, such as Plant Vogtle Units 3 and 4, including Public Service Commission approvals and NRC actions; under certain specified circumstances, a decision by holders of more than 10% of the ownership interests of Plant Vogtle Units 3 and 4 not to proceed with construction and the ability of other Vogtle owners to tender a portion of their ownership interests to Georgia Power following certain construction cost increases; the ability to construct facilities in accordance with the requirements of permits and licenses (including satisfaction of NRC requirements), to satisfy any environmental performance standards and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction; the inherent risks involved in operating and constructing nuclear generating facilities; the ability of counterparties of Georgia Power to make payments as and when due and to perform as required; the direct or indirect effect on Georgia Power's business resulting from cyber intrusion or physical attack and the threat of physical attacks; catastrophic events such as fires, earthquakes, explosions, floods, tornadoes, hurricanes and other storms, droughts, pandemic health events, political unrest or other similar occurrences; and the direct or indirect effects on Georgia Power's business resulting from incidents affecting the U.S. electric grid or operation of generating or storage resources. Georgia Power expressly disclaims any obligation to update any forward–looking information.

 

Cision View original content to download multimedia:http://www.prnewswire.com/news-releases/final-module-placed-for-vogtle-3--4-project-301276479.html

SOURCE Georgia Power



Serious News for Serious Traders! Try StreetInsider.com Premium Free!

You May Also Be Interested In





Related Categories

PRNewswire, Press Releases

Related Entities

Twitter