VSB Group Connects One of Europe's Largest Repowering Projects to the Grid
DRESDEN,
More energy, less land use
The new wind farm produces 235 gigawatt hours of electricity per year – enough to supply around 67,000 three-person households, comparable to a city the size of Heidelberg. "Every kilowatt hour from Repowering Wind Farm Elster strengthens
Repowering sets new standards
With an efficiency increase of nearly 600 percent, the Elster site demonstrates the vast potential of repowering. This strategy is particularly promising in countries like
Future-proof development of existing sites
VSB has been involved with the Elster location for over two decades. Between autumn 2021 and autumn 2022, the legacy turbines were dismantled. Many of their components were given a second life – either reused for spare parts or in continued operation elsewhere.
"Grid connection, permitting, dismantling – the project posed significant challenges in every phase," points out
European technology, measurable benefits
The 16 SG 6.6-155 turbines come from European manufacturer Siemens Gamesa. "Modern turbines like the SG 6.6-155 deliver higher yields using less land – and make a clearly measurable contribution to climate protection," adds
Expansion starts this autumn
Two additional turbines will be added in autumn 2025. For Grolman, the path forward is clear: "Fewer turbines, more output, and smart use of available land – that's the key to a strong European wind industry."
Fact box: Old turbines vs. new turbines
Former wind farm (decommissioned turbines) | Repowered wind farm | |
Number of turbines | 50 | 16 |
Turbine type | Enercon E-40 | Siemens Gamesa |
Commissioning | Between 2000 and 2002 | 2025 |
Capacity per turbine | 0.6 MW | 6.6 MW |
Total installed capacity | 30 MW | 105.6 MW |
Annual energy yield | 36 GWh | 235 GWh |
Hub height | 77.8 metres | 165 metres |
Rotor blade length | 20 metres | 77.5 metres |
Total height (tip) | 97.8 metres | 242.5 metres |
Detailed information as well as image and video material related to the announcement
https://vsb.canto.global/b/VKVK6
Photos of the opening ceremony will be available via the link from 1:45 p.m. (CEST) on 15 August.
Further information on the Repowering Wind Farm Elster www.windfarm-elster.com
About VSB Group
VSB, headquartered in Dresden, is one of
Photo - https://mma.prnewswire.com/media/2748903/VSB_Group_Elster_wind_farm.jpg
Logo - https://mma.prnewswire.com/media/2667274/5456451/VSB_Logo.jpg
View original content to download multimedia:https://www.prnewswire.com/news-releases/vsb-group-connects-one-of-europes-largest-repowering-projects-to-the-grid-302530270.html
SOURCE VSB Group
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Cleafy Named a Leader in QKS Group SPARK Matrix™: Enterprise Fraud Management, 2026
- German Federal Court of Justice issues landmark ruling in case brought by Alisher Usmanov against the EU Council - German law firm Rechtsanwälte Steinhöfel
- MetaOptics Provides Information Guidance on ADS Conversion and Issuance Process
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!





Tweet
Share