New Transformer Installed and Energized in Downtown Bradford Substation
Get Alerts FE Hot Sheet
Join SI Premium – FREE
New Penelec equipment to enhance electric service reliability for more than 1,000 customers
The substation's previous transformer experienced an issue last fall and could not be repaired. A mobile substation provided temporary service to customers until a new transformer could be located, transported and installed to help ensure long-term grid stability.
The new transformer measures 7-feet by-4-feet, stands 11 feet tall and weighs nearly 40,000 pounds. A large crane hoisted the unit over the substation fence and onto a concrete foundation. Electricians installed new electric cables in the substation to power the transformer's forced-air cooling fans, which provide more capacity than the former transformer that relied on natural air circulation to cool. Access into the substation was also enhanced to prevent utility trucks from blocking the street when using the front gate.
With the new transformer in place and operating properly, the mobile substation has been disconnected and is ready for deployment to where it is needed next.
Photos of a crane removing the old transformer from the Bradford West Substation near the University of Pittsburgh's
The work is part of Energize365, a multi-year grid evolution program focused on transmission and distribution investments that will deliver the power FirstEnergy's customers depend on today while also meeting the challenges of tomorrow. With planned investments of
Earlier this year, Penelec completed a significant forestry project to improve electric service reliability for customers in the
As part of that effort, contractor Aerial Solutions used a helicopter saw to trim trees along a 13-mile power line running through rugged, heavily wooded terrain from a substation in
Penelec serves approximately 597,000 customers within 17,600 square miles of northern and central
FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in
View original content to download multimedia:https://www.prnewswire.com/news-releases/new-transformer-installed-and-energized-in-downtown-bradford-substation-302286106.html
SOURCE FirstEnergy Corp.
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Evan Sandberg Wins 20th Annual Arizona State Poker Championship
- Holladay Distillery Helps Bring Made for KC Barbecue Championship to Weston
- Illinois American Water Announces Upcoming Hydrant Flushing in Villa Grove
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share