Minesto AB: Interim Management Statement 1 January - 31 March 2025
CEO Dr
Significant events January-
In February, Minesto welcomes Faroese stakeholders, authorities as well as the public to a seminar at the Nordic House in Torshavn. CEO
An independent technical review of Minesto´s Dragon-class technology initiated in autumn 2024 is completed by DNV – a world leader in technology assessments and certifications in the energy & maritime sectors, incl. renewable energy solutions. The successfully completed review strengthens Minesto's buildout investment case.
Minesto is selected to participate in GIA (Global Innovation Accelerator). The Global Innovations Accelerator Programme is initiated and funded by the Swedish Energy Agency, and run together with partner Business Sweden. Minesto's focus will be on strengthening business development in
Minesto is selected by renowned bearing manufacturer SKF to be part of a large-scale international marketing brand campaign. The campaign 'The Faroe Islands Space Program – a space program that never leaves earth' highlights Minesto's innovative and lightweight yet powerful tidal energy kites; and the opportunity to harness 'moon energy', making the most of the Earth's resources in a sustainable approach.
After the end of the period
After the end of the period, a total of 9,906,055 warrants of series TO4 were exercised, corresponding to approximately 89.0 percent of all outstanding warrants. Guarantee commitments amounted to 1,221,727 shares, which corresponded to approximately 11.0 percent of the outstanding TO4 warrants. As a result, the warrants were exercised in full, reaching 100 percent, and the subscription price was
The Group in summary 1 January-
- Total operating income for the period amounted to
SEK 6,298 thousand (6,791) and mainly consist of capitalised development work. - Operating loss for the period amounted to
SEK 10,697 thousand (–11,794). The negative result is largely attributable to business development and administration related to technology development. During the period, personnel costs ofSEK 6,298 thousand (6,712) has been capitalised as development work. - At the end of the period, the intangible assets amounted to
SEK 553,664 thousand (508,537), of which capitalised development costs amounted toSEK 536,192 thousand (492,016), and capitalised patent expenses ofSEK 17,471 thousand (16,520). - Grants of
SEK 246 thousand (439) were accounted for during the period, of whichSEK 246 thousand (425) has reduced the acquisition value of the capitalised development costs. - At the end of the period, cash flow amounted to
SEK -24,317 thousand (-1,844). At the end of the period, cash and cash equivalents amounted toSEK 10,334 thousand (13,595). - At the end of the period, equity amounted to
SEK 557,716 thousand (511,171) divided into 194,116,040 shares (160,732,694), of which loss for the period amounted toSEK 10 843 thousand (–11,574).
The Interim Management Statement is available to download at Minesto's website:
www.minesto.com/investor/investor-information
CEO comment:
Record public exposure and solid progress
"We have had an intense first quarter in the
Business development work on our major next step – Hestfjord Phase 1 of 10MW – is moving forward with progress in important areas such as environmental permitting, verifications of site measurements and outlining of manufacturing set-up to deliver multiple kites.
Notably, the energy content in the tidal flows for Hestfjord in the
In close dialogue with key suppliers, we have also designed a set-up for manufacturing of the first batches of multiple large scale kites including supply chain logistics, system assembly and onshore testing. We have a unique ocean renewable technology in many aspects, whereof one is the ability to rely on serial production in a manufacturing process instead of 'one-off' shipyard-based build.
Our external communication has reached new record levels that safely can only be described as unique for a tech development company like ours. The collaboration with our strategic partner SKF on a '
In addition, we have been invited and are actively involved in three different market development programs supported by the EU and the Swedish Energy Agency in markets such as
Despite all the turmoil in the world, Minesto is relentlessly determined to offer our much needed and highly competitive renewable baseload energy technology at scale. More than ever, our unique technology is demanded by nations seeking energy independence and security, as well as a resilient system of renewable, affordable and dispatchable energy."
/
For additional information, please contact:
Cecilia Sernhage, Chief Communications Officer
+46 735 23 71 58
[email protected]
This information was brought to you by Cision http://news.cision.com
https://news.cision.com/minesto-ab/r/interim-management-statement-1-january---31-march-2025,c4143237
The following files are available for download:
Interim Management Statement Q1 2025_Minesto AB | |
https://mb.cision.com/Public/14621/4143237/b0023d921942d441.pdf | Press Release |
View original content:https://www.prnewswire.com/news-releases/minesto-ab-interim-management-statement-1-january--31-march-2025-302442354.html
SOURCE Minesto AB
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Trilogy Metals Reports Second Quarter Fiscal 2026 Results and Provides Update on Federal Permitting Progress and Project Advancement
- OneMain Holdings Announces Date of Second Quarter 2026 Earnings Release and Conference Call
- Handspring Raises $19M Series B to Bring High-Quality Mental Health Care to Children and Families Nationwide
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesRelated Entities
Definitive AgreementSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share