Buscar Company Provides Updated Permitting Status for Treasure Canyon Mine
EXECUTIVE SUMMARY
The Company has taken meaningful steps in the permitting process for the
QUALIFIED PERSON
The Company has engaged
PERMITTING STATUS UPDATE
Plan of Operations — Current Status
Under
Specifically, the Forest Service has directed the Company to review comments previously provided by Forest Minerals Officer
The Company is preparing a revised and complete Plan of Operations to address the Forest Service's comments. The Forest Service has stated that upon receipt of a final, complete Plan of Operations, its resource specialists will schedule a site visit to collect GPS shapefiles, verify access routes, and document existing site conditions.
Multi-Agency Permit Coordination
The Company is coordinating with the following regulatory agencies to obtain necessary permits:
- Water Rights – California State Water Resources Control Board
- Streambed Alteration / Bridge Permit – California Department of Fish & Wildlife (CDFW)
- County Permits & Land Use Approvals – Plumas County Planning Department
- Air Quality Permits – Sierra County Air Pollution Control District
- Wastewater Discharge Permit – California Regional Water Quality Control Board
- SMARA Compliance – California Department of Conservation, Division of Mine Reclamation
The Forest Service has confirmed receipt of a temporary bridge permit previously issued by CDFW; however, the Company has been advised that this permit expires in 2026, and the Forest Service has recommended that the Company seek an extension. The Company notes that placement of any bridge on National Forest System lands will require separate District Ranger authorization following Plan of Operations approval and completion of environmental review.
All other required agency applications remain pending. Required engineering design work for the access road, bridge crossing, and water retention/treatment systems is nearing completion, with final engineering drawings expected to be submitted to the relevant agencies within 14 days of this release.
Permit Timeline Expectations
No permits have been approved to date. The commencement of the Forest Service's environmental review is contingent upon submission of a complete Plan of Operations and confirmation that all required permits and waivers are being actively pursued, as required under 36 CFR 228.4 and 228.5. Based on typical timelines for similar projects in
- State Water Resources Control Board permits: 30–60 days
- CDFW Streambed Alteration Agreement: 30–60 days
- SMARA approval: 30–60 days
- Air quality permits: 30–60 days
- County land use approvals: approximately 30 days
These timelines are estimates only. The permitting process involves multiple regulatory agencies with independent review timelines and discretionary authority. There can be no assurance regarding the timing of permit approvals, the conditions that may be imposed, or whether all required permits will be obtained.
On-site fieldwork is anticipated to commence only after all necessary permits are obtained and is subject to favorable weather conditions and site accessibility.
MANAGEMENT COMMENTARY
"We are committed to providing our shareholders with accurate and transparent information," said
EXPLORATION STAGE PROPERTY — NO MINERAL RESERVES
About Buscar Company
Buscar Company (OTC Markets Pink: CGLD) is a mineral exploration company focused on gold and precious metals opportunities. Through its wholly owned subsidiary Eon Discovery Inc., the Company maintains mining claims on the
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995, including statements regarding the Company's plans for completing its Plan of Operations, obtaining regulatory permits, conducting field exploration, and the anticipated timelines for regulatory review. These statements involve substantial risks and uncertainties. Important factors that could cause actual results to differ materially include: the Company's status as an exploration stage issuer with no established mineral reserves or operating revenue; its ability to prepare a Plan of Operations satisfactory to the U.S. Forest Service; its ability to obtain required permits from multiple agencies; uncertainty regarding the timing and outcome of permit applications; the possibility that permit conditions may require significant additional capital expenditures; the Company's need for additional financing; risks inherent in mineral exploration; dependence on third-party consultants; weather and site accessibility limitations; commodity price fluctuations; environmental risks; potential regulatory changes; and risks associated with OTC Markets Pink-quoted companies. The Company does not undertake to update these forward-looking statements except as required by law.
Contact:
CEO,
Buscar Company
[email protected]
View original content to download multimedia:https://www.prnewswire.com/news-releases/buscar-company-provides-updated-permitting-status-for-treasure-canyon-mine-302726844.html
SOURCE Buscar Company (CGLD)
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Harvard discloses $2.2B SpaceX stake, over half its U.S. equity portfolio
- Andersen Group launches secondary offering of 4.28M shares
- RedCloud signs 3-year Argentina deal, forecasting $20m revenue
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share