Mcewen Mining (MUX) Reports FY18 and Q4 Production Results
Get Alerts MUX Hot Sheet
Join SI Premium – FREE
McEwen Mining Inc. (NYSE: MUX) reports annual consolidated production in 2018 was 135,124 gold ounces and 3,032,727 silver ounces, or 175,561 gold equivalent ounces(1)(“GEOs”).
Consolidated Production Summary
| Q4 | Full Year | Full Year2018 Guidance | |||
| 2017 | 2018 | 2017 | 2018 | ||
| Gold (oz) | 48,609 | 29,291 | 109,947 | 135,124 | 128,000 |
| Silver (oz) | 926,739 | 819,473 | 3,178,742 | 3,032,727 | 3,225,000 |
| GEOs(1) | 60,965 | 40,217 | 152,329 | 175,561 | 171,000 |
| (1) Using a 75:1 gold to silver ratio. | |||||
2018 Production
Black Fox Mine, Timmins, Canada (100%) – Gold
Black Fox produced 48,848 GEOs in 2018, in line with our full year production guidance of 48,000 GEOs. Q4 production from Black Fox was 11,097 GEOs. To continue to build on the success of the 2018 exploration program at the Black Fox and Stock properties, a $15 million flow through share financing was completed in Q4 to fund exploration in 2019.
San José Mine, Argentina (49%(2)) – Silver & Gold
San José produced 47,331 gold ounces and 3,020,696 silver ounces, for a total of 87,607 GEOs attributable to us in 2018, below our full year guidance of 91,000 GEOs. Our attributable production in Q4 was 12,602 gold ounces and 816,374 silver ounces, for a total of 23,487 GEOs.
El Gallo Project, Mexico (100%) – Gold
El Gallo produced 39,106 GEOs in 2018, exceeding our full year production guidance of 32,000 GEOs. By the end of Q2 2018, mining and crushing activities at El Gallo ceased and were followed by residual heap leaching, which resulted in production of 5,633 GEOs in Q4. Closure, reclamation and residual heap leaching activities are ongoing and will continue for several years.
Development
Gold Bar Mine, Nevada, USA (100%) – Gold
Construction at Gold Bar is near completion and on schedule for inaugural gold production in Q1 2019. Activities at Gold Bar in Q4 focused on commissioning utilities and ore delivery systems, and mechanical completion of the gold processing plant. Site buildings and infrastructure are complete and occupied. Mining, crushing, loading of the heap leach pad, and parts of the processing plant are active. Remaining activities include electrical work and instrumentation installation in the gold processing plant, and commissioning of the gold refinery circuit.
Fenix, Mexico (100%) – Silver & Gold
Work on the Fenix Project, which is evaluating the potential construction of a new mine and mill at El Gallo, is ongoing. During the first half of 2019 we expect to complete the feasibility study, and receive regulatory approval for a permit amendment to allow for in-pit tailings storage, which is a key feature of the proposed project implementation.
Financial Results
Operating costs for the quarter ended December 31, 2018 will be released with our 10-K Annual Financial Statements in late February 2019.
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- McEwen Copper seeks $1.6b in equity financing for Los Azules - Bloomberg
- BJ's Wholesale Club (BJ) Tops Q2 EPS by 19c, Beats on Revenue; Offers FY27 EPS Guidance
- Kimbell Royalty closes $221.2M mineral rights acquisition
Create E-mail Alert Related Categories
Corporate News, GuidanceRelated Entities
Twitter, Dividend, EarningsSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share