Soluna Holdings (SLNH) Announces Monthly Business Update
Get Alerts SLNH Hot Sheet
Join SI Premium – FREE
Soluna Holdings, Inc. (“SHI” or the “Company”), (NASDAQ: SLNH), a developer of green data centers for intensive computing applications including Bitcoin mining and AI, announced its September project site-level operations, developments, and updates.
The Company has provided the following Corporate and Site Updates.
Key Company Metrics:
The monthly metrics are now available here.
Corporate Highlights:
- Term Sheets for Project Rosa – Soluna signed a term sheet with a renewable energy leader for Project Rosa, boosting capacity by 187 MW of sustainable energy for AI and Bitcoin mining.
- CEO John Belizaire attended the 2024 Ai4 Conference – A recording of the panel “The AI Ecosystem: Hardware, Cloud, and Enterprise Integration” can now be viewed here.
- New Blog – We unpack the problems and novel solutions to AI’s bottomless energy appetite. Read it here.
- New Blog – We explore the convergence of artificial intelligence and renewable energy and the resulting innovative solutions. Read it here.
Key Project Updates:
Project Dorothy 1A (25 MW, Bitcoin Hosting) / Project Dorothy 1B (25 MW, Bitcoin Prop-Mining):
- The Four Coincident Peak (4CP) period ended in September with our MaestroOS(™) control system successfully responding to all demand requirements.
- Optimization efforts to include building insulation, heat shielding, and power infrastructure cooling solutions have been completed.
- We successfully completed the summer program for our participation in ancillary services.
Project Dorothy 2 (48 MW, Bitcoin Hosting):
- Site grading will be completed in the coming weeks.
- Civil construction teams are in the process of pouring concrete pads for the initial phase of work with MDC fabrication underway so building erection can follow shortly after.
- All long lead power infrastructure has been received.
- Dates to complete the substation interconnection are in the process of being finalized with work slated to begin in December.
New Project Grace (2 MW at Dorothy 2, AI Cloud/Hosting):
- Kicked off kW Mission Critical on the Concept design for Helix.
New Project Ada (1 MW, AI Cloud with HPE):
- 6 POCs in progress or completed with partners or potential customers.
- New sales team in contract negotiations with several customers to fill the initial Cluster.
- Demand for an additional 84 Nodes (or 672 GPUs) is on the waitlist.
- Attracted leading aggregators to our Cloud platform.
Project Sophie (25 MW, Bitcoin Hosting with Profit Share, AI Hosting):
- The site has continued to operate at a high level as cooler temperatures persist into the fall season.
- Preparations are underway for an 8.8 MW fleet upgrade and 3.3 MW expansion of an existing customer to be completed in October.
Project Kati (166 MW, Bitcoin Hosting and AI):
- Meter Design Proposal Submitted to AEP
- Negotiations continue with landowners for the site land leases.
View Soluna’s recent AMA here.
View Soluna 2024 Earnings Power Presentation here.
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Crude Inventory Fell 4.5M Barrels Last Week - EIA
- Cronos expands Spinach cannabis edibles and vape lineup in Canada
- Caesars Entertainment (CZR) 1K contracts of September 30 calls trade
Create E-mail Alert Related Categories
Corporate NewsRelated Entities
Twitter, Earnings, Bitcoin, Maynard Um, Mark Zuckerberg, ARKSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share