Graphite One Enters FAST-41 60-Day Planning and Timetable Period
FAST-41 process requires G1's coordinated project plan and timetable to be posted to the public Federal Permitting Dashboard no later than
FAST-41 projects receive Record of Decision on average 25% faster than non-FAST-41 projects
FAST-41 process commences as new IEA Report notes that global graphite dependence on
Administered by the Federal Permitting Improvements Steering Council ("FPISC"), the FAST-41 timetable includes intermediate and final completion dates for each required federal environmental review and authorization.
The project's lead Federal agency – in the case of Graphite One, the U.S. Army Corps of Engineers – must work with other cooperating agencies to develop project-specific plans to document the steps they will take to coordinate public and tribal participation and complete the required environmental reviews and authorizations.
This timetable will be published to the FAST-41 Federal Dashboard no later than
Benefits of FAST-41
As the FPISC has reported:
"…on average, projects supported through FAST-41 achieved Record of Decision faster than those that did not leverage FAST-41 by nearly 25%."
Twenty-five additional mining projects are listed on the Federal Transparency dashboard, established by Presidential Executive Order on
Infrastructure projects covered under FAST-41 benefit in the following ways:
Increased visibility and predictability. Agencies must develop and maintain a coordinated, project-specific timetable for all required environmental review and permitting actions. Scheduled and actual timeframes for these actions are publicly displayed and updated quarterly on the Permitting Dashboard. FAST-41 states that the lead Federal agency cannot revise or extend a timetable end date within 30 days of the original end date. FAST-41 also states that a final completion date for an environmental review or authorization must not be extended by more than 30 days without consulting with the project sponsor.
Enhanced coordination. Within 60 days of a project becoming covered under FAST41, the lead Federal agency must work with other cooperating agencies to develop project-specific plans to document the steps they will take to coordinate public and tribal participation and complete the required environmental reviews and authorizations. Advanced coordination allows for early communication of project goals to the permitting agencies, early discussion of alternatives, and alignment of agency review schedules.
Increased accountability. The Permitting Council provides high-level oversight to ensure that Federal agencies adhere to established timetables. The Permitting Council must report to Congress when the total length of modifications to a permitting timetable delays the permitting process by more than 150% of the original schedule. In addition, an annual report to Congress is required to assess each agency's progress towards implementation of FAST-41 best practices, as well as their compliance with recommended performance schedules for covered projects.
The FAST-41 Federal Permitting Dashboard may be accessed here.
Figure 1: Raw Material Ownership by Country 2024 1
1 G1's entry into the FAST-41 process comes as a new International Energy Agency ("IEA") report indicates that
The full IEA Report may be found here.
______________________________ | |
1 | |
Graphite One's Domestic Supply Chain Strategy
With
About Graphite One Inc.
GRAPHITE ONE INC. continues to develop its Graphite One Project (the "Project"), with the goal of becoming an American producer of natural and synthetic graphite anode materials that is integrated with a domestic graphite resource. The Project is proposed as a vertically integrated enterprise to mine, process and manufacture high grade anode materials primarily for the lithium–ion electric vehicle battery market.
On Behalf of the Board of Directors
"Anthony Huston" (signed)
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Cautionary Note Regarding Forward-Looking Statements
All statements in this release, other than statements of historical facts, including those related to the Fast 41 listing and the anticipated impact of the FAST-41 status, any statements related to the planned production of any mineral reserves and resources, the construction of the
View original content to download multimedia:https://www.prnewswire.com/news-releases/graphite-one-enters-fast-41-60-day-planning-and-timetable-period-302481791.html
SOURCE Graphite One Inc.
Serious News for Serious Traders! Try StreetInsider.com Premium Free!
You May Also Be Interested In
- Azitra Announces Adjournment of 2026 Annual Meeting and Information for Reconvened Meeting
- B. Riley Securities to Host Mind, Muscle & Vision Healthcare Summit on July 16, 2026
- Bio Ascend™, a Vaniam Group™ Company, Assumes Stewardship of iwNHL™ and iwMyeloma™ Workshops, Building on the Longstanding Leadership of World Health Communications
Create E-mail Alert Related Categories
PRNewswire, Press ReleasesSign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!



Tweet
Share