Bitdeer bitcoin output rises 388% Y/Y to 990 BTC in June
Bitdeer Technologies Group (NASDAQ: BTDR) mined 990 bitcoin in June 2026, a 388% increase from the same month a year earlier, according to the company's unaudited monthly operations update.
The Singapore-based company reported a self-mining hash rate of 73.0 EH/s, up from 70.2 EH/s in May 2026 and 16.5 EH/s in June 2025. Co-mining hash rate, involving Bitdeer's rigs operated by third-party data centers, reached 15.9 EH/s. Total mining rigs under management rose to 289,000, compared with 277,000 in May. Bitdeer held 150 bitcoin at the end of June.
On the AI cloud side, annualized revenue run rate reached approximately $76 million at a 95% utilization rate, up from approximately $69 million and 90% utilization in May. The company had 4,248 GPUs deployed and 3,517 under external subscription.
Bitdeer signed a 10-year lease for a new data center in Johor Bahru, Malaysia, providing 21.7 IT MW of capacity, with handover expected in Q1 2027. The facility is planned to support 128 Nvidia GB300 NVL72 systems. The company also executed a lease for a colocation AI data center site in Tydal, Norway, subject to certain conditions.
Bitdeer also announced a groundbreaking for a Sealminer manufacturing facility in Sparks, Nevada, targeted for completion by the end of 2026.
"Bitcoin production of 990 BTC, up 388% year-over-year, and self-mining hashrate of 73.0 EH/s reflect continued strength across our mining platform," said Michael G. Potter, Chief Financial Officer of Bitdeer.
Total global electrical capacity stood at approximately 3,025 MW, combining 1,797 MW of online capacity and 1,228 MW in the pipeline.