Georgia Power continues focus on improving reliability through Grid Investment Program
Company completes 100+ grid projects and major system upgrades statewide in 2025
In 2025 alone, the Grid Investment program executed 104 distribution system projects, surpassing its original target of 88, and advanced 25 major transmission projects, including five transmission line upgrades and 20 substation enhancements. To date, these efforts have improved reliability for more than 504,000 customers.
Upgrades also deliver value for customers during severe weather events, helping reduce service interruptions and making work in the field more efficient. Following Winter Storm Fern in January, Georgia Power restored power to 175,000 within the first 24 hours and, following Hurricane Helene in
"Our priority is delivering clean, safer, and reliable energy for every customer we serve. The progress made last year shows how strategic grid investments directly improve reliability and restoration speed, especially during severe weather," said
Examples of local projects in 2025 include:
Southwest Atlanta (Ben Hill ) - A grid improvement project employed a mix of investment types to achieve reliability goals, including pole strengthening improvements and sectionalizing. This project involved installing stronger poles and equipment throughout the circuit. These upgrades help improve line performance during weather events, improving reliability for local customers.Stone Mountain – Grid projects incorporate a mix of investment types to improve reliability. These projects involved installing outage isolation equipment to divide the circuit into smaller sections, allowing outages to be isolated and restored more quickly. Combined with stronger poles and hardware upgrades, these improvements enhance system performance and reliability for customers in the area.Wilmington Island /Savannah –The Wilmington Island project inSavannah replaced overhead power lines with underground lines to reduce exposure to trees, weather, and vehicles. This underground work helps prevent outages and enhances reliability for customers in the area.
Since the start of the Grid Investment Program in 2020, Georgia Power has completed many large-scale improvements across its system, including: upgrades to 364 circuits and substations; installation of 5,500 advanced devices; replacement or enhancement of 39,000 poles; and installation of 500 miles of underground cable.
Reliability is measured in two ways: frequency of service interruptions, or "System Average Interruption Frequency Index" (SAIFI), and duration of service interruption, or "System Average Interruption Duration Index" (SAIDI). On average, areas where Georgia Power has completed a Grid Investment project experience up to a 50% improvement in both metrics. Customers positively impacted by these projects are now experiencing about half as many outages, and about half as much interruption time.
To learn more about the Grid Investment Program, including active projects in communities across
About Georgia Power
Georgia Power is the largest electric subsidiary of Southern Company (NYSE: SO), America's premier energy company. Value, Reliability, Customer Service and Stewardship are the cornerstones of the company's promise to 2.8 million customers in all but four of
View original content to download multimedia:https://www.prnewswire.com/news-releases/georgia-power-continues-focus-on-improving-reliability-through-grid-investment-program-302734872.html
SOURCE Georgia Power