Close

Eldorado Gold (EGO) Provides 2021 Guidance and Five-Year Outlook

January 14, 2021 5:37 PM EST

Eldorado Gold Corporation, (NYSE: EGO) today provided detailed 2021 production and cost guidance and an updated five-year production outlook.

Highlights

  • Kisladag high-pressure grinding roll (HPGR) commissioning in the third quarter of 2021 and pre-stripping investments position the mine for sustained free cash flow over a 15-year mine life.
  • Increased five-year production profile at Lamaque driven by increasing mining rates and efficiencies from completion of Triangle decline in 2021.
  • Column flotation at Efemcukuru improves concentrate grade and enhances low costs and operational consistency to drive sustained cash flow.
  • Throughput expansion and efficiency improvements at Olympias lead to new growth phase over the five-year plan.
  • Strong liquidity to drive further debt reduction in 2021.

The Company’s 2021 gold production is forecast to be between 430,000 and 460,000 ounces at all-in sustaining costs (AISC) of $920 to $1,150 per ounce. Average 2021 cash operating costs are forecast in the range of $590 to $640 per ounce of gold sold. Quarter-to-quarter gold production in 2021 is expected to be relatively consistent with higher anticipated gold grade at Kisladag in the first half of the year expected to be offset by lower head grade at Lamaque. In the second half of 2021, gold production at Lamaque is expected to increase on higher grade while production at Kisladag will be temporarily affected by the expected third-quarter commissioning of the HPGR circuit.

“Eldorado’s strong five-year production profile provides the growth and flexibility to reinvest in our portfolio of mines and projects while also continuing to deleverage our balance sheet,” said George Burns, Eldorado Gold’s President and Chief Executive Officer. “In Greece, we continue to work productively with the government on discussions and permitting to re-start construction at Skouries; the completion of which will drive new production growth beyond our current five-year plan.”

Five-Year Gold Production Outlook

Production (oz)2021E2022E2023E2024E2025E
Kisladag140,000 - 150,000140,000 -150,000165,000 -175,000185,000 - 195,000160,000 - 170,000
Lamaque140,000 - 150,000165,000 - 175,000180,000 - 190,000160,000 - 170,000185,000 - 195,000
Efemcukuru*90,000 - 95,00080,000 - 85,00080,000 - 85,00075,000 - 80,00075,000 - 80,000
Olympias55,000 - 65,00055,000 - 60,00065,000 - 70,00080,000 - 90,00090,000 - 100.000
Total430,000 - 460,000430,000 - 460,000480,000 - 510,000500,000 - 530,000510,000 - 540,000

* Forecast production at Efemcukuru has been adjusted for reduced payable ounces following a change in structure of concentrate sales contracts. Lower payability is offset by a decrease in forecast production costs, due to the elimination of treatment charges and other deductions.

2021 Cost and Capital Expenditure Guidance

2021E 2021E
Consolidated Costs Olympias
Cash Operating Cost – C1 ($/oz sold)590-640 Cash Operating Cost – C1 ($/oz sold)775-825
Total Operating Cost – C2 ($/oz sold)680-730 Total Operating Cost – C2 ($/oz sold)900-950
AISC ($/oz sold)920 -1,150 Sustaining Capex ($ millions)38 - 43
Kisladag Corporate ($ millions)
Cash Operating Cost – C1 ($/oz sold)590-640 General and Administrative32
Total Operating Cost – C2 ($/oz sold)700-750 Exploration125 - 30
Sustaining Capex ($ millions)18 - 23
Growth Capital ($ millions)
Lamaque Kisladag90 - 95
Cash Operating Cost – C1 ($/oz sold)560-610 Olympias10 - 15
Total Operating Cost – C2 ($/oz sold)580-630 Lamaque35 - 40
Sustaining Capex ($ millions)48-53
Other Project Spending ($ millions)
Efemcukuru Skouries25 - 30
Cash Operating Cost – C1 ($/oz sold)550-600 Stratoni10 – 15
Total Operating Cost – C2 ($/oz sold)680-730 Perama Hill5 - 10
Sustaining Capex ($ millions)18 - 23 Tocantinzinho3 – 5
Certej3 – 5

1 55% expensed and 45% capitalized.

Kisladag

In 2021, Kisladag is expected to mine and place on leach over 11 million tonnes of ore at an average grade of 0.69 grams per tonne. Subsequent to the commissioning of the HPGR circuit in the third quarter, recoveries are expected to improve substantially in the second half of 2021 with average recoveries at approximately 50% for the year.

Forecast 2021 sustaining capital of $18 to $23 million is primarily for work related to the cover liner, ADR columns and equipment overhauls. Growth capital of $90 to $95 million is expected to consist primarily of the HPGR project, waste stripping and construction of the North Leach Pad. A portion of the expenditure on the HPGR project has shifted from 2020 to 2021; however, the HPGR circuit is expected to be fully operational on schedule by the end of the third quarter. Phase 1 of the North Leach Pad facility is expected to be ready for stacking by the end of the third quarter.

Efemcukuru

In 2021, Efemcukuru is expected to mine and process almost 520,000 tonnes of ore at an average gold grade of 6.6 grams per tonne. Cash operating costs per ounce in 2021 are expected to increase due to fewer payable gold ounces sold, partially offset by the weakening of the Turkish Lira. Forecast total cash costs and AISC have increased due primarily to higher gold royalty rates consistent with higher gold prices. Expected sustaining capital expenditures for 2021 include drilling related to KPR resource conversion as well as 2020 carry-over capital expenditures.

Lamaque

In 2021, Lamaque is expected to mine and process over 750,000 tonnes of ore at an average gold grade of 6.6 grams per tonne. 2021 cash operating costs per ounce of $560 to $610 reflect mining at increasing depth, which is expected to be partially offset by increased mining rates.

Sustaining capital expenditures for 2021 are forecast to be approximately $48 to $53 million, to be allocated primarily on capitalized underground mine development and infrastructure as vertical access to the Triangle deposit continues for infill drilling and future production. Growth capital projects in 2021 include continued work on the Triangle decline as well as additional mining equipment purchases and modest mill upgrades toward achieving 2,200 tonne-per-day capacity. Engineering studies and initial preparation for tailings placement are also included. This work will continue over the outlook period.

The five-year outlook for Lamaque reflects an increase in mining rates to 2,500 tonnes per day, achieved primarily through accelerating underground development. The Company continues to evaluate expansion of the Sigma mill to accommodate higher mining rates at Triangle as well as potential mill feed from satellite deposits. However, until such time as a mill investment decision has been made and construction completed, any excess production above 2,200 tonnes per day is assumed to be toll milled at a neighboring facility.

Olympias

In 2021, Olympias is expected to mine over 443,000 tonnes of ore at an average grade of 7.3 grams per tonne of gold, 104 grams per tonne of silver, 3% lead and 4% zinc. Forecast 2021 ore processed includes processing of old tailings. Payable production is expected to be 55,000 to 65,000 ounces of gold, 1.1 million to 1.2 million ounces of silver, 11,000 to 11,500 tonnes of lead metal and 11,500 to 12,000 tonnes of zinc metal. Improving production rates and efficiency improvements are beginning to drive a moderating cash operating cost profile. Cash operating costs, net of by-products, are expected to decrease to $775 to $825 per ounce of gold sold.

Forecast 2021 sustaining capital expenditures of $38 to $43 million include underground mine development and the second phase of tailings management facility construction. Growth capital expenditures at Olympias of $10 to $15 million include process plant expansion and contractor development to support planned ramp-up to 650k tonnes per year.

2021 Commodity and Currency Price Assumptions

Gold ($/oz)$1,750
Silver ($/oz)$25
Lead ($/mt)$1,950
Zinc ($/mt)$2,400
C$/US$1.3:1
EURO$/US$ 1:1.20
US$/TRY7.7:1

Strengthening our Team

Eldorado also announced today the appointments of Brock Gill and Simon Hille as well as the promotion of Sylvain Lehoux to the role of Vice President & General Manager, Québec.

Brock Gill will join the Company as Senior Vice President, Projects & Transformation in March. Brock will oversee development engineering activities, project delivery of major capital projects, and transformation through business improvement initiatives. He previously held the role of Vice President, Projects with BHP where he was responsible for leading the multi-billion-dollar Jansen Potash Project and other key development projects.

Simon Hille joined Eldorado in November, 2020 as Vice President, Technical Services. He is responsible for technical projects and fostering innovation throughout the Company. Prior to joining Eldorado, Simon was with Newmont (Goldcorp), as Group Executive, Technical Engineering and Global Projects. Ahead of the Newmont merger, Simon was Vice-President, Global Innovation, Metallurgy and Processing at Goldcorp. He also held progressively senior leadership roles in metallurgy and process development with Barrick Gold and Newcrest Mining. Simon has over 30 years of experience in gold and base metals specializing in leading high-performance, cross-functional technical and operational teams to maximize value from complex ore bodies.

Sylvain Lehoux was promoted to the role of Vice President & General Manager, Québec in early December 2020. He will continue to oversee all mine site operations in Québec while also taking on increased responsibilities as an ambassador for Eldorado in the region. Sylvain joined Eldorado in June 2017 as General Manager of the Company’s Lamaque mine. Prior to that, he was General Manager of the Westwood Mine with IAMGOLD Corporation and held the role of Vice President Operations with Alexis Minerals.



Serious News for Serious Traders! Try StreetInsider.com Premium Free!

You May Also Be Interested In





Related Categories

Corporate News, Guidance, Management Changes, Management Comments

Related Entities

Definitive Agreement