Las Vegas Sands Corp. (NYSE: LVS) disclosed an extended deadline was granted on Parcel 3 in Cotai, Macao.
From the Filing:
As previously reported, the deadline for Sands China Ltd., a subsidiary of Las Vegas Sands Corp. with ordinary shares listed on The Stock Exchange of Hong Kong Limited, to complete SCL's development of Parcel 3 in Cotai, Macao was April 2013 and SCL intended to apply for an extension from the Macao Government of that deadline. SCL made that application in February 2012.
On July 16, 2012, SCL announced that on July 13, 2012, the Macao Government informed SCL that, by a decision of the Secretary for Transportation and Public Works, the extension of the construction period relating to Parcel 3 was authorized up to April 17, 2016. SCL also was informed that it will be notified about the penalty amount which shall be payable by SCL due to the delay of the construction period. SCL’s announcement is attached as Exhibit 99.1 to this report and is incorporated by reference into this item.
Join StreetInsider.com FREE and get immediately alerted when news breaks on your stocks and other market items - JOIN NOW
*NEW - Download StreetInsider's FREE iPhone and iPad App - Click Here
From the Filing:
As previously reported, the deadline for Sands China Ltd., a subsidiary of Las Vegas Sands Corp. with ordinary shares listed on The Stock Exchange of Hong Kong Limited, to complete SCL's development of Parcel 3 in Cotai, Macao was April 2013 and SCL intended to apply for an extension from the Macao Government of that deadline. SCL made that application in February 2012.
On July 16, 2012, SCL announced that on July 13, 2012, the Macao Government informed SCL that, by a decision of the Secretary for Transportation and Public Works, the extension of the construction period relating to Parcel 3 was authorized up to April 17, 2016. SCL also was informed that it will be notified about the penalty amount which shall be payable by SCL due to the delay of the construction period. SCL’s announcement is attached as Exhibit 99.1 to this report and is incorporated by reference into this item.
Join StreetInsider.com FREE and get immediately alerted when news breaks on your stocks and other market items - JOIN NOW
*NEW - Download StreetInsider's FREE iPhone and iPad App - Click Here
You May Also Be Interested In
- BofA/Merrill Lynch Sees Upside in Las Vegas Sands (LVS)
- BioLineRx (BLRX) Enters $20M ATM Offering w/ Stifel
- Morgans Hotel Group (MHGC) Clarifies Yucaipa Statements
Create E-mail Alert Related Categories
Corporate NewsLogin with Facebook
Sign up for StreetInsider Free!
Receive full access to all new and archived articles, unlimited portfolio tracking, e-mail alerts, custom newswires and RSS feeds - and more!